FACILITY
Integrated Iron & Steel Plant at Kalinga Nagar industrial complex, at Orissa state, India
TASK COMPLETED:
Warming up of coke oven battery №1 (H=7m.) with liquefied gas:
- preparatory work;
- warming up of coke oven battery;
- charging and start-up of coke oven battery;
- start-up of chemical recovery shop;
- adjustment of machines' and mechanisms' operating mode;
- adjustment of coke ovens' heating mode;
- training of the personnel.
2004
Warming up of coke oven battery №1 (H=7m.) with liquefied gas:
- preparatory work;
- warming up of coke oven battery;
- charging and start-up of coke oven battery;
- start-up of chemical recovery shop;
- adjustment of machines' and mechanisms' operating mode;
- adjustment of coke ovens' heating mode;
- training of the personnel.