FACILITY
West Siberian Integrated Iron-and-Steel Plant, Novokuznetsk, Kemerovo region, Russia
TASKS COMPLETED:
• Adjustment of bracing system for operating Coke oven battery No.1:
- inspecting the conditions of the flashplates, oven door frames and buckstays;
- resetting the proper load values for all anchorage spring units.
• Repeated regulation and heating mode adjustment of operating Coke oven battery No.7:
- adjusting and tuning up the process mode for various coking times;
- cleaning and decarbonising of sole ducts and regenerators, gas burners and gas-supply fittings of all the heating walls;
- grouting (gunniting) of gas riser pipes for all the heating walls;
- resetting loads on all the anchorage spring units and adjusting the COB bracing system.
2022
• Repeated regulation and heating mode adjustment of operating Coke oven battery No.1.
2020
• Technical supervision for the hot repairs of COB No.4 2019 Health inspection of coke oven batteries No.1 and Nos.4 – 7.
2018
• Master contract on reconstruction of complex of coke oven batteries № 1, 2:
- design of coke oven batteries complex №№1, 2;
- complete delivery of refractories for coke oven battery №1;
- delivery of refractories for repair - operational needs;
- construction-assembly work on coke oven battery №1;
- designer's technical supervision over construction of coke oven battery №1.
1996-2006
• Appraisal of industrial safety of coke oven batteries №№ 3, 4, 5, 6, 7, shop and intershop gas mains of by-product-coke plant.
2000
• Adjustment of bracing system for operating Coke oven battery No.1:
- inspecting the conditions of the flashplates, oven door frames and buckstays;
- resetting the proper load values for all anchorage spring units.
• Repeated regulation and heating mode adjustment of operating Coke oven battery No.7:
- adjusting and tuning up the process mode for various coking times;
- cleaning and decarbonising of sole ducts and regenerators, gas burners and gas-supply fittings of all the heating walls;
- grouting (gunniting) of gas riser pipes for all the heating walls;
- resetting loads on all the anchorage spring units and adjusting the COB bracing system.
2022
• Repeated regulation and heating mode adjustment of operating Coke oven battery No.1.
2020
• Technical supervision for the hot repairs of COB No.4 2019 Health inspection of coke oven batteries No.1 and Nos.4 – 7.
2018
• Master contract on reconstruction of complex of coke oven batteries № 1, 2:
- design of coke oven batteries complex №№1, 2;
- complete delivery of refractories for coke oven battery №1;
- delivery of refractories for repair - operational needs;
- construction-assembly work on coke oven battery №1;
- designer's technical supervision over construction of coke oven battery №1.
1996-2006
• Appraisal of industrial safety of coke oven batteries №№ 3, 4, 5, 6, 7, shop and intershop gas mains of by-product-coke plant.
2000